On July 13, 2023, the foundation act commemorating the expansion of the wastewater treatment plant in Sulejówek with elements of the biological treatment unit was embedded in the foundation slab of the secondary settling tank.
At the beginning of July, deliveries of technological equipment under the contract "Construction of a biomass boiler with a nominal capacity of 7MW in SPGK Sp. z o.o."
In Brzuchania, sliding works of the radar tower are underway. The execution technology requires work 24 hours a day, so we do not slow down at night either.
Works related to the modernization of the wastewater treatment plant in Żyrardów are nearing finishing point. Most of the facilities have been completed, the new biogas tank is already in operation.
Instal Warszawa awarded in the "Friendly Workplace" competition. An award granted by Manpower, a global leader in HR solutions since 2012, to reward companies that stand out for their care for creating a friendly atmosphere in the workplace.
On June 5, 2023, Instal Warszawa signed with Zakład Gospodarki Komunalnej in Góra Kalwaria contract for the task "Modernization of the wastewater treatment plant in Moczydłów - stage II".
On Friday, May 26, 2023, Instal Warszawa signed a contract with PEC Siedlce for the task "CONSTRUCTION OF A GAS COGENERATION WITH A CAPACITY OF APPROXIMATELY 8 MWe".
As part of the 15th Conference-Roadshow Mechanical and biological waste treatment organized by ABRYS, the participants visited the construction site at the Wielkopolskie Centrum Recyclingu in Jarocin on May 17, 2023.