This is the second biological treatment line that is being renovated at the RADOCHA II wastewater treatment plant in Sosnowiec. With each reactor put back into operation, our actions become more and more repeatable.

We start with demolition, then concrete walls dividing the denitrification and nitrification chambers are built, and in parallel, preparatory work is carried out to repair and protect the walls and bottom of the reactors, as well as the coatings themselves. And then it's all downhill - assembly, commissioning and the next sequence. And so on until four... And there are two reactors in each train.