Within the task: Construction and reconstruction of a sludge and gas line, a sludge dewatering and thickening node and a cogeneration station for the sewage treatment plant in Chrzanów Duży the construction of all newly designed and modernized facilities has been completed. Works in the field of road and green areas have started.
The performance of repairs and protective coatings of concrete structures is coming to an end.
In the modernized sludge dewatering and thickening station, works related to the assembly of devices, i.e. centrifuges and thickener, as well as technological installations are in progress.
In the I&C industry, work is underway on the installation of control and measurement equipment necessary to start the commissioning of individual facilities and to launch a new SCADA.