Transport of two oil-fired water boilers with a nominal heat output of 20 MWt each and one gas-oil water boiler with a nominal heat output of 5 MWt arrived at the construction site. It is another milestone on the way to adapt the Pruszków Combined Heat&Power Plant to the requirements of DIRECTIVE OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL (EU) 2015/2193 of 25 November 2015 on the reduction of emissions of certain pollutants into the air from medium combustion plants (MCP).
In addition, the investment is underway, works on the foundations and walls of the gas-oil boiler room and pumping station are advanced, the installation of an oil storage tank V = 800 m3, as well as technological trestle bridges.
The commissioning of the gas-oil boiler house is planned for the first quarter of 2023.